The following modernization projects, led by Computer Sciences Corp., are under watch by officials from the Internal Revenue Service and Congress
The following modernization projects, led by Computer Sciences Corp., are under watch by officials from the Internal Revenue Service and Congress:
Project: e-Services
Function: Web-based administrative applications, such as issuing tax preparer identification numbers.
Revised cost estimate: $130 million — $86 million over original estimate.
Revised completion date: April 20, 2005 — 1 year behind schedule.
Project: Customer Account Data Engine Release 1
Function: Database management system for taxpayer account data.
Revised cost estimate: $97 million — $36 million over original estimate.
Revised completion date: June 30, 2005 — 2 1/2 years behind schedule.
Project: Integrated Financial System Release 1
Function: General ledger accounting system.
Revised cost estimate: $153 million — $53 million over original estimate.
Revised completion date: Project schedule is under review.
Source: General Accounting Office