GAO: Spawar skips testing
Report says Spawar buys large quantities of a system before completing operational testing
Actions to Improve Navy SPAWAR Low-Rate Initial Production Decisions
The Navy's Space and Naval Warfare Systems Command regularly rolls out large portions of information systems in the early stages of contracts before those systems have undergone testing, the General Accounting Office reports.
Spawar buys the equipment in an attempt to provide new information systems to the fleet as soon as possible, a GAO report released this month states. But a review of several of the systems found that six had experienced operational problems that hurt the fleet, GAO said.
The problem arises from Spawar buying and rolling out information technology systems in relatively large quantities—sometimes exceeding 50 percent of the total—at the early stage of a program before completing operational testing, the report said.
"Buying systems before completing operational testing has inherent risks, and Spawar's practice of buying high percentages of a system's total inventory objective during low-rate initial production raised these risk concerns," GAO said.
The main purpose of low-rate initial production is to produce enough units for operational testing and evaluation and to establish production capabilities to prepare for full-rate production, GAO said. "Limited initial production affords the opportunity to confirm the stability and soundness of a new system before producing larger quantities," GAO said in the report, "Defense Acquisitions: Actions to Improve Navy SPAWAR Low-Rate Initial Production Decisions."
GAO reviewed eight of the 21 fielded Spawar programs with a high percentage of low-rate initial production quantities and found that "all had performance problems, all had interoperability problems, and six had suitability problems," the report said.
The report quotes Navy officials as saying it is important to get information systems into action quickly. "Officials in the Office of the Chief of Naval Operations said the fleet would rather have an information system with 75 to 80 percent capability than to wait until Spawar completes all necessary testing to ensure a system will meet all of its capability," the report said.
Furthermore, the Spawar commander told GAO that these purchases are considered low-risk because they use proven commercial technologies and are relatively low-cost items when compared with the cost of ships and aircraft.
GAO, however, said that Spawar and the Navy have taken steps to assess the risk of projects and provide greater discipline in its buying procedures.
"The GAO investigation and report were helpful to Spawar in taking an objective look at the command's [low-rate initial production] acquisition strategy," Spawar spokesman Richard Williamson said. "Spawar will continue to move as rapidly as possible to deploy advanced command, control, communications and information technology to the fleet" to ensure that the fleet has the equipment necessary for success.
NEXT STORY: Online case file limits proposed